Archived Community Updates
For past construction and community updates*, please use the links below:
- Construction Update July 2018
- Construction Update September 2018
- Construction Update October 2018
- Construction Update November 2018
- Construction Update December 2018
- Construction Update February 2019
- Construction Update March 2019
- Construction Update April 2019
- Construction Update May 2019
- Construction Update June 2019
- Construction Update July 2019
- Construction Update August 2019
- Construction Update September 2019.
- Construction Update October 2019.
- Construction Update November 2019.
- Construction Update December 2019.
- Construction Update February 2020.
- Construction Update March 2020.
- Construction Update April 2020.
- Construction Update May 2020.
- Construction Update June 2020.
- Construction Update July 2020.
- Construction Update August 2020.
- Construction Update September 2020.
- Construction Update October 2020.
- Construction Update November 2020.
- Construction Update December 2020.
- Construction Update February 2021.
- Construction Update March 2021.
- Construction Update April 2021.
- Construction Update May 2021.
- Construction Update June 2021.
- Construction Update July 2021.
- Construction Update August 2021.
- Construction Update September 2021.
- Construction Update October 2021.
- Construction Update November 2021.
- Construction Update December 2021.
- Community Update February 2022.
- Community Update March 2022.
- Community Update April 2022.
- Community Update May 2022.
- Community Update June 2022.
- Community Update July 2022.
- Community Update August 2022.
- Community Update - September 2022.
- Community Update - October 2022.
- Community Update - November 2022.
- Community Update - December 2022.
- Community Update February 2023.
- Community Update March 2023
- Community Update April 2023
- Community Update May 2023
* We use the term ‘commissioned’ in this context to mean that all turbines had undertaken a commissioning test. However due to a number of factors some turbines had to undergo further construction works to be able to pass their grid commissioning and reliability tests. The final turbine in MNWF was commissioned on the 1 April 2022 after completing its construction works and passing its grid commissioning and reliability test.